Interpret Task Duration Settings

The requirements for qualification on a Task differ on a Task-by-Task basis.  For some Tasks, once you have completed the Task the first time, you will never have to review the information again.  For other Tasks, it may be more important to review information on a regular basis - to ensure that the proper procedure is both known and is being followed.

A graphic illustration of a Task that is either complete or incomplete is as follows:

(Learner answers Knowledge Assessment questions or Supervisor answers Capability Assessment questions on behalf of the Learner)

However, if you have a Task that requires review from time to time, you can introduce the concept of duration.  TRACCESS CI (8.0) introduced a new property for a Task - that either component (Knowledge and/ or Capability) could have a duration, and that these could be different values.  The possible resulting icons are:

OR OR OR OR

In TRACCESS CI (8.2), not only can you set separate durations for the Knowledge and Capability components which are measured in days, but you can also set a fixed date duration on a Task.  Although the resulting icons appear the same, their function is slightly different.  Both types of duration are set using the Component Duration Settings dialog (that can be accessed in the Properties section, when a Task is selected in the Process Manager tree).

For example:

Task:  Comply with CPR.  CPR must be recertified every 3 years.  This can be accomplished in a few ways:

Number of Days Duration Example

When an Employee completes the Task components for Comply with CPR, the program will begin to count down when the Task will be required to be recertified.  The following variables were used for this situation:

                                                  

Feb 28, 2004           March 1, 2004        Jan 30, 2007     to be completed before March 1, 2007

Fixed Date Duration Example

Regardless of when an Employee completes the Task components for Comply with CPR, the Task is set to expire on a set date.  The following variables were used for this situation:

At this point, two different options can be set.  The SME may wish for the Task components to elapse on this date, and not allow requalification to occur before (likely because new information is to be implemented on this date).  Conversely, the SME may wish for the Employee to be able to complete the Task components in a short time period before they elapse - resulting in qualification for the following period.  If you wish for the first case to occur, you must set the Allow Re-qualification within __ days of expiry to 0.  If you wish for the second case to occur, you must set the number of days in this dialog.

Please note:  the warning period for a Task that has a fixed date duration is set in the Duration Setting dialog, and has nothing to do with the option in the Tools/ System Options dialog.

Fixed Date Example (with no allowance for requalification)

                                    

Feb 28, 2004           March 1, 2004            Jan 1, 2007

Fixed Date Example (with 10 days allowance for requalification)

                                                  

Feb 28, 2004           March 1, 2004            Dec 21, 2006   to be completed before Jan 1, 2007

 

Information about Number of Days vs Fixed Date durations