The Delete Unassigned Employees dialog appears.
The Delete Results dialog appears.
The Delete Unassigned Tasks dialog appears.
The Delete Results dialog appears.
The Delete Unassigned Resources dialog appears.
The Delete Results dialog appears.
Please note: If you have removed a Task from all of its Processes, and a Resource remained assigned to this Task, the Task is considered unassigned, but the resource is still assigned. To be able to delete the resource, you will either have to reassign the Task to a Sub Process and remove the resource, or delete the Task and the resource will become unassigned.
|
|
|