Purging Objects
To Purge Unassigned Employees
- Select Tools/ Maintenance/ Unassigned Employees/
Purge from the main menu.
The Purge Archived Employees dialog appears.
- Highlight an Employee from the Archived Employees box,
click >> and click OK.
The Purge Results dialog appears.
- Click OK.
To Purge Unused Tasks
- Select Tools/ Maintenance/ Unused Tasks/ Purge
from the main menu.
The Purge Archived Tasks dialog appears.
- Highlight a Task from the Archived Tasks box, click >>
and click OK.
The Purge Results dialog appears.
- Click OK.
To Purge Unused Tasks
- Select Tools/ Maintenance/ Unused Resources/
Purge from the main menu.
The Purge Archived Resources dialog appears.
- Highlight a Resource from the Archived Resources box, click
>> and click OK.
The Purge Results dialog appears.
- Click OK.